1. Cement
|
1,20,000
|
2. Sand
|
90,000
|
3. Gravel
|
40,500
|
4. Steel
|
1,80,000
|
5. Bricks
|
60,900
|
6. Tiles
|
58,500
|
7. Paint
|
45,000
|
Total Material Cost (1 to 7)
|
5,94,900
|
8. Labour cost Foundation+Upto Brick work
|
3,00,000
|
9. Other Services Electrical, Sanitory, Painting
|
1,00,000
|
Labour+Other (8+9)
|
4,00,000
|
Windows (3% On Material Cost)
|
17,847.00
|
Doors (3.4% On Material Cost)
|
20,226.60
|
Plumbing (5.5% On Material Cost)
|
32,719.50
|
Electrical (6.8% On Material Cost)
|
40,453.20
|
CP+Sanitary (4.17% On Material Cost)
|
24,807.33
|
Total Fitting Cost
|
1,36,053.63
|
Total Cash Required : 11,30,953.63 per 1000 SQFT.